PAVING – Driveway and Road Resurfacing
Resurface and Paving Project
This schedule is subject to change due to weather or unforeseen delays. Residents will be notified of any changes.
Work hours are 7:00 AM–5:00 PM. Please move all vehicles before work begins.
Subject: Berkshire Ridge Roadway Paving Project – Schedule & Access Restrictions
Dear Residents,
Mark Paving has provided the final roadway paving schedule for next week. The attached map identifies the areas included in each phase of the project. The yellow highlighted roadways represent Phase 1, and the green highlighted roadways epresent Phase 2.
Phase 1 (Yellow Highlighted Areas)
- Milling: Tuesday, October 27
- Paving: Wednesday, October 28
Roadways included in Phase 1:
- Irontown Circle
- Ridge Road Entrance
- Ogdon Court
- Petersburg Court
- Ridgeview Court
- Schofield Court
- Pine Hollow Court
- Davenport’s Mill Court
- Stonehouse Court
- Ridge Road Entrance of Falcon Drive up to Irontown Circle
Phase 2 (Green Highlighted Areas)
- Milling: Thursday, October 29
- Paving: Friday, October 30
Roadways included in Phase 2:
- Falcon Drive
- Preston King Court
- Heritage Court
- Red Oak Terrace
- Berkshire Valley Road Entrance
Access Restrictions
VERY IMPORTANT: IF YOU ARE PARKING IN YOUR DRIVEWAY, THE END OF YOUR VEHICLE MUST BE AT LEAST 6 FEET FROM THE INSIDE EDGE OF THE CURB TO PROVIDE ADEQUATE CLEARANCE FOR THE PAVING MACHINES. IF YOU CANNOT PARK CLOSE ENOUGH TO YOUR HOUSE TO MAINTAIN THIS 6-FOOT CLEARANCE, YOU MUST PARK YOUR VEHICLE AT ANOTHER LOCATION. THIS ALSO APPIES TO GUEST PARKING SPACES AS WELL.
On milling days, roadways within the active work area will be closed to through traffic. Residents may still access driveways, mail delivery, and trash collection, provided paving operations are not obstructed and caution is exercised around construction equipment.
On paving days, the affected roads will be completely closed to all vehicle traffic beginning at 7:00 a.m. and will remain inaccessible until paving operations are complete and the asphalt has cooled sufficiently for traffic. This is expected to be approximately two hours after paving work is completed.
VERY IMPORTANT: IF YOU ARE PARKING IN YOUR DRIVEWAY, THE END OF YOUR VEHICLE MUST BE AT LEAST 6 FEET FROM THE INSIDE EDGE OF THE CURB TO PROVIDE ADEQUATE CLEARANCE FOR THE PAVING MACHINES. IF YOU CANNOT PARK CLOSE ENOUGH TO YOUR HOUSE TO MAINTAIN THIS 6-FOOT CLEARANCE, YOU MUST PARK YOUR VEHICLE AT ANOTHER LOCATION. THIS ALSO APPIES TO GUEST PARKING SPACES AS WELL.
Please review the attached map carefully to determine which phase affects your home and plan accordingly. Additional parking and access information will be distributed prior to the start of work.
We appreciate your patience and cooperation as we complete these roadway improvements for the community.
Thank you,
Homestead Management Services
On behalf of the Berkshire Ridge Board of Trustees

As part of the ongoing paving project, the visitor parking lot adjacent to the clubhouse must remain completely empty at all times. This area has been designated for paving equipment, contractor vehicles, and project staging.
No parking is permitted in the visitor lot near the clubhouse until further notice. Any vehicles parked in this area may interfere with the paving operations and could be subject to towing at the owner’s expense.
We appreciate your cooperation and patience as we work to improve the community. Please use alternate parking locations and allow extra time when traveling through the property during construction.
This schedule is subject to change due to weather or unforeseen delays. Residents will be notified of any changes.
Resurface and Paving Project
This schedule is subject to change due to weather or unforeseen delays. Residents will be notified of any changes.
Work hours are 7:00 AM–5:00 PM. Please move all vehicles before work begins.
Subject: Berkshire Ridge Roadway Paving Project – Schedule & Access Restrictions
Dear Residents,
Mark Paving has provided the final roadway paving schedule for next week. The attached map identifies the areas included in each phase of the project. The yellow highlighted roadways represent Phase 1, and the green highlighted roadways epresent Phase 2.
Phase 1 (Yellow Highlighted Areas)
- Milling: Tuesday, October 27
- Paving: Wednesday, October 28
Roadways included in Phase 1:
- Irontown Circle
- Ridge Road Entrance
- Ogdon Court
- Petersburg Court
- Ridgeview Court
- Schofield Court
- Pine Hollow Court
- Davenport’s Mill Court
- Stonehouse Court
- Ridge Road Entrance of Falcon Drive up to Irontown Circle
Phase 2 (Green Highlighted Areas)
- Milling: Thursday, October 29
- Paving: Friday, October 30
Roadways included in Phase 2:
- Falcon Drive
- Preston King Court
- Heritage Court
- Red Oak Terrace
- Berkshire Valley Road Entrance
Access Restrictions
VERY IMPORTANT: IF YOU ARE PARKING IN YOUR DRIVEWAY, THE END OF YOUR VEHICLE MUST BE AT LEAST 6 FEET FROM THE INSIDE EDGE OF THE CURB TO PROVIDE ADEQUATE CLEARANCE FOR THE PAVING MACHINES. IF YOU CANNOT PARK CLOSE ENOUGH TO YOUR HOUSE TO MAINTAIN THIS 6-FOOT CLEARANCE, YOU MUST PARK YOUR VEHICLE AT ANOTHER LOCATION. THIS ALSO APPIES TO GUEST PARKING SPACES AS WELL.
On milling days, roadways within the active work area will be closed to through traffic. Residents may still access driveways, mail delivery, and trash collection, provided paving operations are not obstructed and caution is exercised around construction equipment.
On paving days, the affected roads will be completely closed to all vehicle traffic beginning at 7:00 a.m. and will remain inaccessible until paving operations are complete and the asphalt has cooled sufficiently for traffic. This is expected to be approximately two hours after paving work is completed.
VERY IMPORTANT: IF YOU ARE PARKING IN YOUR DRIVEWAY, THE END OF YOUR VEHICLE MUST BE AT LEAST 6 FEET FROM THE INSIDE EDGE OF THE CURB TO PROVIDE ADEQUATE CLEARANCE FOR THE PAVING MACHINES. IF YOU CANNOT PARK CLOSE ENOUGH TO YOUR HOUSE TO MAINTAIN THIS 6-FOOT CLEARANCE, YOU MUST PARK YOUR VEHICLE AT ANOTHER LOCATION. THIS ALSO APPIES TO GUEST PARKING SPACES AS WELL.
Please review the attached map carefully to determine which phase affects your home and plan accordingly. Additional parking and access information will be distributed prior to the start of work.
We appreciate your patience and cooperation as we complete these roadway improvements for the community.
Thank you,
Homestead Management Services
On behalf of the Berkshire Ridge Board of Trustees

Resurface and Paving Project
This schedule is subject to change due to weather or unforeseen delays. Residents will be notified of any changes.
| ADDRESS | DAY 1 EXCAVATION | DAY 2 PAVING | DAY 3 CURING |
| DAVENPORT’S MIL CT 1,2,4,6 + guest parking | MON 10/12 Excavation | MON 10/12 Paving Off limits once paving begins | TUE 10/13 NO VEHICLES Access resumes 8 AM Wed 10/15 |
| STONEHOUSE COURT 1–17 + guest parking | MON 10/12 Excavation Use after 5 PM | TUE 10/13 Paving Off limits once paving begins | WED 10/14 NO VEHICLES Access resumes 8 AM Thu 10/15 |
| HERITAGE COURT 1–20 + guest parking | TUE 10/13 Excavation Use after 5 PM | WED 10/14 Paving Off limits once paving begins | THU 10/15 NO VEHICLES Access resumes 8 AM Fri 10/16 |
| PRESTON KING TRAIL 1–16 + guest parking | WED 10/14 Excavation Use after 5 PM | THU 10/15 Paving Off limits once paving begins | FRI 10/16 NO VEHICLES Access resumes 8 AM Sat 10/17 |
| RED OAK TERRACE 2–28 + guest parking | THU 10/15 Excavation Use after 5 PM | FRI 10/16 Paving Off limits once paving begins | SAT 10/17 NO VEHICLES Access resumes 8 AM Sun |
| RED OAK TERRACE 30–60 + guest parking | FRI 10/16 Excavation Use after 5 PM | MON 10/19 Paving Off limits once paving begins | TUE 10/20 NO VEHICLES Access resumes 8 AM Wed 10/21 |
| RED OAK TERRACE 62–84 + guest parking | MON 10/19 Excavation Use after 5 PM | TUE 10/20 Paving Off limits once paving begins | WED 10/21 NO VEHICLES Access resumes 8 AM Thu 10/22 |
| OGDON COURT 1–16 + guest parking | TUE 9/29 Excavation Use after 5 PM | WED 9/30 Paving Off limits once paving begins | THU 10/1 NO VEHICLES Access resumes 8 AM Fri 10/2 |
| PETERSBURG COURT 1–20 + guest parking | WED 9/30 Excavation Use after 5 PM | THU 10/1 Paving Off limits once paving begins | FRI 10/2 NO VEHICLES Access resumes 8 AM Sat 10/3 |
| RIDGEVIEW TERRACE 1–19 + guest parking | THU 10/1 Excavation Use after 5 PM | FRI 10/2 Paving Off limits once paving begins | SAT 10/3 NO VEHICLES Access resumes 8 AM Sun 10/4 |
| RIDGEVIEW TERRACE 21–39 + guest parking | FRI 10/2 Excavation Use after 5 PM | MON 10/5 Paving Off limits once paving begins | TUE 10/6 NO VEHICLES Access resumes 8 AM Wed 10/7 |
| SCOFIELD COURT 1–19 + guest parking | MON 10/5 Excavation Use after 5 PM | TUE 10/6 Paving Off limits once paving begins | WED 10/7 NO VEHICLES Access resumes 8 AM Thu 10/8 |
As part of the ongoing paving project, the visitor parking lot adjacent to the clubhouse must remain completely empty at all times. This area has been designated for paving equipment, contractor vehicles, and project staging.
No parking is permitted in the visitor lot near the clubhouse until further notice. Any vehicles parked in this area may interfere with the paving operations and could be subject to towing at the owner’s expense.
We appreciate your cooperation and patience as we work to improve the community. Please use alternate parking locations and allow extra time when traveling through the property during construction.
Berkshire Ridge Driveway Paving Notice – Summary
Work Begins: September 29, 2026
Work Hours: 7:00 AM to 5:00 PM
Residents must move all vehicles before work begins each day.
Once paving begins, driveways must remain completely free of vehicles throughout the paving and curing period until 8:00 AM the following morning. The schedule may change due to weather or unforeseen circumstances, and residents will be notified of any updates.
REVISED DRIVEWAY REPAVING SCHEDULE – WORK BEGINS SEPTEMBER 29 2026
| Work hours are 7:00 AM–5:00 PM. Please move all vehicles before work begins. |
This schedule is subject to change due to weather or unforeseen delays. Residents will be notified of any changes.
IMPORTANT PARKING RULE
After paving begins, the driveway must remain completely free of vehicles through the full curing day, until 8:00 AM the following morning.
This schedule is subject to change due to weather or unforeseen delays. Residents will be notified of any changes.
Thank you for your cooperation.
Subject: Berkshire Ridge Paving Project Q&A
Dear Berkshire Ridge Residents,
We will be holding a brief Q&A session regarding the upcoming paving project.
Date: Thursday, September 17, 2026
Time: 6:30 PM
This is an opportunity to ask questions and receive updates about the project. We hope you can join us.
Topic: Berkshire Ridge – Q&A for Paving Project
Time: Sep 17, 2026 06:30 PM Eastern Time (US and Canada)
Join Zoom Meeting
https://zoom.us/j/92836414228?pwd=L3j3XMhkamXSUNGu60bly8XOJQamHu.1
Meeting chat link
https://zoom.us/launch/jc/92836414228
View meeting insights
https://zoom.us/launch/edl?muid=8f20db6c-be73-4b77-bf91-7f078ea11769
Meeting ID: 928 3641 4228
Passcode: 564653
One tap mobile
+13092053325,,92836414228#,,,,*564653# US
+13126266799,,92836414228#,,,,*564653# US (Chicago)
Join by SIP
Join instructions
https://zoom.us/meetings/92836414228/invitations?signature=05iUCN0h54Qpz-8Bp_Cy2ZPr9Qb5uTyGxEfWT2Bs6w0
Best Regards,
Lloyd Sleeper
Community Manager
Dear Neighbors,
As we move forward with our parking lot, driveway, and roadway paving projects, please review the materials at your earliest convenience. These documents contain important information regarding the project schedule, procedures, and expectations.
We also ask for your help in reaching neighbors who may not regularly use computers or who may have difficulty accessing the attached information. A few minutes of assistance can make a big difference in ensuring everyone understands the process and is prepared for the upcoming work.
Together, we can help make these improvements proceed as smoothly as possible for the good of our community.
Thank you for your support, cooperation, and consideration.
The Board of Directors
On behalf of our community
Berkshire Ridge Driveway Schedule Public
BERKSHIRE RIDGE PAVING – PARKING RULES
Parking Rules during road resurfacing at Berkshire Ridge
Schedule: Right now, we are on schedule to begin the week after Labor Day, weather permitting. All residence will be notified when they are scheduled to have their driveways removed.
Patience. All 218 residents are going to be inconvenienced at some point during this project. Please be considerate of your neighbors and the vendor who we have selected for this major undertaking.
We will completely remove and replace all 218 driveways first before we begin the roads along with all the guest parking areas.
To provide the vendor with adequate access to your driveway and remove all the old blacktops, we ask that you leave your garage doors open only during the time the vendor is working on your street. Sorry for the inconvenience but we don’t want any accidents with their excavation equipment and your garage door.
Of course you can close them at night.
When it’s your turn to have your driveway replaced, we ask you not to park in guest parking on that street as that is being replaced also.
We ask that you relocate your car(s) to the grass area either on Iron Town Circle or Falcon Drive and park there until after your new driveway has been installed.
Once the new driveway is installed you may walk on it after 3 hours.
After the new driveway is installed, you may park on it after 4 days.
However, DO NOT turn your steering wheel when parked on the new driveway. The power steering will dig a hole in the new blacktop. Failure to comply will cause repair work at your expense.
After the driveways are all installed, we will begin milling and repaving the roads.
Please avoid the section of road that is being worked on. For example: When they are working on Falcon Drive from the Ridge Road entrance to the top of the hill by the pool, please use the entrance on Berkshire Valley Road to enter and leave the facility.
We will send out email notices to make you aware of the plan for the following day, so everyone is aware of how to enter and exit.
Once again, we ask everyone to execute patience and some common sense.
Of course, emergency vehicles will have 100% access as needed.
Anyone who feels inconvenienced should recognize that nice newly poured driveways and roadways will increase the value of your home.
On behalf of your board of directors, We thank you for your cooperation.